Before You Sign a Lease in West Texas, Ask About the Power
In West Texas right now, the most important line item on a site selection checklist isn’t square footage, lease rate, or highway access.
It’s electricity.
That might sound like an overstatement. It isn’t. Power availability has quietly moved to the top of the conversation in industrial real estate across this region — and the businesses that find out too late are the ones who signed first and asked questions second.
The Grid Is Under More Pressure Than Most People Realize
West Texas has always been an energy-producing region. What’s changed is that it’s now one of the biggest energy-consuming regions in the country too.
Oil and gas operations across the Permian Basin draw as much electricity at peak times as the entire city of Houston. Add a wave of data centers and new manufacturing facilities on top of that, and you start to see why grid capacity has become a real constraint — not just a talking point.
"The available electrical infrastructure in the Permian Basin was years behind the electrical needs of the industry." — Texas Oil and Gas Association, letter to state regulators
Things have improved in some areas since that letter was written. But not everywhere, and not fast enough to keep up with the demand coming into this market.
Getting Power to a New Site Takes Longer Than You'd Expect
Connecting a new industrial facility to the grid isn’t like flipping a switch. You need a substation with available capacity. You need transformers — and lead times on large transformers are running around two and a half years right now nationally, because demand has outpaced supply by a wide margin. Sometimes you need new transmission infrastructure entirely, which stretches timelines out even further.
Texas approved the Permian Basin Reliability Plan — a $13+ billion transmission project — specifically because the grid couldn’t keep pace with growth out here. That’s real money and a real commitment. But transmission lines take years to permit and build. The fix is coming. It’s just not here yet.
In a lot of West Texas locations today, getting power confirmed and connected is the longest lead item in the entire project. Not the building. Not the permits. The power.
Three Questions to Ask Before You Commit to a Site
The deals that go smoothly are the ones where power gets treated as a first question, not something to sort out after the letter of intent is signed. Here’s what’s worth knowing upfront:
- How much power is actually confirmed at this site — right now? Not estimated. Not “there’s a substation nearby.” A utility letter or feasibility study that backs it up.
- Who is the serving utility, and what’s their timeline to connect you? In West Texas that’s typically Oncor or AEP depending on location. Each has its own process and its own queue. Worth knowing which one you’re dealing with and what they’ve told the landlord.
- Is there anything between you and your energization date? A substation upgrade, a transformer on order, a pending transmission project. One question upfront has kept more than one deal from turning into an expensive surprise.
The Bottom Line
West Texas is a strong industrial market. Land availability, workforce, logistics, energy resources — the fundamentals are solid, and the business climate here genuinely supports growth.
But the grid is a real constraint, and the market knows it. Properties with confirmed, available power command a premium — and that gap is widening, not closing, as demand keeps climbing.
Ask the power question early. It changes what you’re looking at and how you evaluate it.
Questions about power-ready industrial sites in West Texas? I'm happy to talk through what I'm seeing in the market.